Power & Parliamentary Affairs minister KG Kenye disclosed that out of Nagaland’s total 633 MW hydro power potential, which includes both operational and identified capacities, only 104 MW has been harnessed, leaving 529 MW still untapped.
The minister made this revelation during the Development of North Eastern Region (DoNER) Summit of the 7th North East States on Power and Energy Mix on the third day of the Ashtalakshmi Mahotsav in Delhi on Sunday.
On transmission infrastructure shortfall and requirements, Kenye said a total transmission capacity of 1150.5 MVA was required in order to meet the projected demand of 360 MW of power by 2032.
Out of the total capacity requirement of 1150.5, existing capacity was 400.5MVA, while 240 MVA was ongoing under North-Eastern Region Power System Improvement Project (NERPSIP), leaving a shortfall of 510 MVA.
He said the remaining 510 MVA had been proposed under the Intra-State Transmission Plan 2030-32 for Nagaland, which had been finalised with the Central Electricity Authority of India (CEA).
He mentioned that the plan comprised construction of nine 132/33 kV substations and 476 km of transmission lines at a total estimated cost of Rs 1,150.68 crore for which funding was required.
He presented the state’s power scenario and submitted immediate requirements.
Kenye expressed his sincere gratitude to the Ministry of DoNER, with special reference to Union Minister Jyotiraditya Scindia, for organising the event, and proposed more platforms of this initiative on rotation in the north-eastern states in future.