Nagaland NewsNFR updates on progress of Dhansiri-Zubza rail line

NFR updates on progress of Dhansiri-Zubza rail line

Northeast Frontier Railway (NFR) has informed Nagaland State Transport (NST) department that 98% physical progress has been achieved in Dhansiri-Shukhovi (16.50 km), 24% in Shukhovi-Pherima (28 km) and 2% in Pherima-Zubza (38 km) sections of the new railway line being constructed between Dhansiri and Zubza.

STATUS OF WORK

 Dhansiri-Shukhovi (16.50 km) 98% physical progress

Shukhovi-Pherima (28 km) 24% physical progress

 Pherima-Zubza (38 km) 2% physical progress

In response to a letter by NST general manager Atovi Kiba Sema requestingquarterly progress report on the Dimapur-Dhansiri-Zubza (Kohima)new railway line construction, NFR stated the project was included in 2006-07, but its progress was adversely impacted due to second wave of Covid-19 and non-availability of industrial oxygen. Estimated to cost Rs 700 crore, land acquisition in the Dhansiri-Sukhovi section has been completed and its target date for commission has been fixed as October 2021.

The second phase, which is the Sukhovi-Pherimasection, has been estimated to cost Rs 2,052 crore and its land acquisition too has been completed. 

According to the NFR letter, one of the tunnels (no.-1; 3484 m) is on critical path and 934 m tunnel work is in progress. March2023 has been fixed as the target date for commissioning Phase-II.

The project cost of the Pherima-Zubza section, which is Phase-III, is Rs 4,159 crore, and its land acquisition too has been completed. Tunnel no.-7; 6.61 m was falling on critical path and March 2026 has been fixed as the target date of commissioning of Phase-III, the letter added.

 

EDITOR PICKS

Demonisation and weaponisation

The introduction of the Foreign Contribution (Regulation) Amendment Bill introduced to the Lok Sabha on March 25, 2026, is as controversial as the government alibi and which has attracted flak from various quarters. Framed as a technical measure to ...