WSYF asks firm to expedite 4th Mile-Niuland road works

Western Sumi Youth Front (WSYF) has expressed serious concern over the non-completion of the road project from NH-29, Central Jail (4th Mile) to Atu Ghoki, Hozukhe, Niuland (Dzubza) river.


In a press release, WSYF president Atokiho Sumi and general secretary Botoho Achumi pointed out that the project work “improvement of road from NH-29, Central Jail to Dzubza river, Niuland (phase-II)” was awarded to M/S Vipe Enterprise through work Order dated March 16, 2022 at a contract price of Rs.24.34 crore.


WSYF stated that as per the terms of the tender and the agreement executed, the road project was to be completed on or before April 15, 2023. However, the firm applied for extension of time (EoT), and the office of the chief engineer, PWD(R&B) extended the scheduled time of completion to August 13, 2023 with “strict directives” to the firm to complete the work within the stipulated time cautioning that no further extension of time would be entertained.
However, WSYF expressed dismay that the firm could not complete the project even after EoT was granted.


The forum stated that on September 26, 2023 when the contractor of the firm was summoned to the office of the chief engineer, PWD(R&B), the contractor assured in the form of an undertaking that the work would be completed by November 30, 2023 as per specifications.


However, WSYF said that even after EoT was granted to the enterprise twice, the road project remained incomplete and the work schedule was behind by more than a year “clearly” showing the “lackadaisical attitude” of the firm and the contractor.


WSYF said it also undertook the inspection of the project and it was observed that the overall physical progress stood at 94.54%, while the overall financial progress stood at 89.60% as on May 22, 2024.


The front reminded that for the past several years people have been eagerly waiting for the upgradation and improvement of the road, which serves as a lifeline for the people of Niuland district and adjoining districts of Wokha, Tseminyu and Kohima. However, it said that the construction time taken has not only seriously impacted the economy of the vendors, entrepreneurs but also the living conditions of the people living in the area.


Further, WSYF said that there had been various concerns raised in different quarters by various civil societies relating to the non-completion of the road project.
Despite repeated directions to the firm for completion of the project, WSYF said the progress of the work was taking place at a snail’s pace.


WSYF has, therefore, directed the M/S Vipe Enterprise to expedite the work progress and complete the work at the earliest with quality workmanship and as per specifications and follow all the requisite guidelines of the DPR. Failing which, WSYF cautioned that it would resort to its own course of action “to protect and safeguard the interest of the general public.”


WSYF also urged the firm to ensure that all necessary resources, including personnel and equipment were allocated to expedite the completion of the project. The youth body stated that executive engineer PWD(R&B) Dimapur division has been directed to strictly monitor the project and submit weekly progress report to the office of the chief engineer, PWD(R&B). In this regard, WSYF urged the department to strictly carry out work inspection regularly. It also cautioned against the payment of the remaining balance without completion of the work project.