Nagaland NewsDDMA Longleng inspects landslide

DDMA Longleng inspects landslide

DIMAPUR: District Disaster Management Authority (DDMA), Longleng, led by Deputy Commissioner W. Manpai Phom, conducted a spot verification of the landslide affected stretch of the Changtongya–Longleng Road (NH 702) on September 15. The inspection team was also joined by the Sub Divisional Officer (Civil), Changtongya, representing the District Administration, Mokokchung.
According to DIPR report, the road stretch between Chainage 5+785 to 6+050 was severely damaged following persistent rainfall on the night of September 11, resulting in complete disruption of vehicular movement. The Changtongya–Longleng Road serves as a vital lifeline for Longleng district, connecting the headquarters with the rest of the state and facilitating the movement of people and essential commodities.
The NHIDCL, along with executing agency Nithin Sai Construction (NSC), has been carrying out continuous debris clearance and restoration works since September 12. However, recurring mudslides and landslides, compounded by the ongoing monsoon, have slowed down the restoration process. Certain local issues at the site were resolved through active coordination and support of the District Administration, Mokokchung.
In view of the situation, the DDMA has issued a travel advisory for light vehicles to use the alternate Tangha–Kangching–Merangkong Road until normal vehicular movement is restored. The alternate route is being maintained by DDMA to facilitate safe passage for light vehicles.
The fresh disruption comes even as the district continues to recover from extensive damages caused by incessant rainfall and landslides since July 19. With restoration efforts still underway in several areas, the latest landslide has placed additional strain on connectivity and disaster response.
Another major concern is the complete stoppage of heavy vehicle movement since September 12, which is likely to impact the transportation of essential commodities, particularly fuel and supplies carried by oil tankers. Prolonged disruption may place further pressure on availability if normal connectivity is not restored soon.
The public has been advised to exercise caution, avoid unnecessary travel along the affected stretch, and strictly follow advisories issued by the District Administration and DDMA until normal vehicular movement resumes.