Adding more to the already crisis-laden power situation, citizens of Dimapur face the bleak prospect of several weeks of total black out after the 20 MVA power transformer at 132 Kv sub-station at Nagarjan caught fire and was completely burnt down Sunday afternoon.
The transformer at Nagarjan sub-station blew up into flames at around 1.30 p.m. There was no report of any casualty or injury.
The affected areas include at least 2/3rd of Dimapur- main town area fed from Metha Sub-Station such as: Full Nagarjan, Half Nagarjan, Thilixu, Naharbari, Chekiye, Rangapahar Army Cantonment, Signal Basti, Thahekhu and Peren district.
This information was contained in a press note issued by Engineer-in-Chief (Power), Er. G. Chishi. He also informed that the supply of power to most part of Dimapur has been affected due to total shutdown imposed by the department for restoration works. While not ruling out that the adjacent transformer may also have been affected, Er. Chishi however said damage was contained due to the timely intervention of fire service from army and Nagaland fire brigade.
He also said that a technical team was despatched to the sub-station to thoroughly ascertaining the cause of the fire. He assured that the report would be made available as soon as possible. While assuring all efforts are being made to restore normal power supply at the earliest, Er. Chishi appealed to all customers/public to cooperate with the department during the period.
It may be pointed out that the Department of Power (DoP) has been living on borrowed time with regard to the system which was always on the verge of near-total collapse.
The bursting of transformers in several places and Sunday’s major fire at Nagarjan confirmed the worst fears of the Power engineers themselves. It may be recalled that the Association of Power Engineers of Nagaland (APEN) has been coming out with various pleas on the government to lift the restrictions for purchase of urgently needed equipments to update and upgrade the system but to no avail.
The state government has downgraded the DoP by treating it like a minor department whereas power remains the very nucleus and blood of progress. 
The purchase of a new 20MVA transformer could take weeks and if the only one remaining also fails then it will be a long cold and dark winter for Dimapur.
Probable causes
(a) Short circuit: A transformer could burn in flames due to any short-circuit which would produce an electric arc of very high heat energy. This high energy initiates a phenomenon called “oil cracking” which primarily produces acetylene and hydrogen which are dangerous combustible gases. 
These combustible gases can exist in at least two ways— either as oil in vapour phase or as mist having explosive properties. The high energy of the short circuit easily sets fire to the combustible gases, which then rapidly expands and explodes producing rapidly oscillating pressure waves. 
(b) Excess voltage: Electrical transformers transfer energy between circuits, switching energy from one voltage to another. But when flooded with too much electricity, the sudden surge can cause a transformer explosion. A chamber full of several gallons of mineral oil keeps the circuits cool, but given too much electricity, the circuits fry and melt, failing in a shower of sparks and setting the mineral oil aflame. Mineral oil, in turn, combusts explosively and rockets transformer scything into the air.
But what can we do to prevent such explosions and loss?
There may be a number of possibilities some of which are as follows:
a) Specify short circuiting test during procurement stage (the best option)
b) Install Transformer protector. This is a passive mechanical system that is activated by the level of transformer tank internal pressure reached during a short circuit. At least two transformers can be simultaneously protected by one device.
c) Install protective system based on the release of superheated water at 180 degrees C.
d) Install protective systems based on the release of powder to suppress the fire and subsequent explosion.
e) Install protective systems based on water and salts.
f) Regularly monitor the condition of existing protective devices and monitor the general health of a transformer, especially for moisture ingress.