Govt has much explanation to do on HC building project: ACAUT

A little over ten years after its foundation stone was laid, the High Court building project at Meriema, Kohima is still incomplete with only 35% of works been completed.
Aggrieved by the inordinate delay in progress of the works of construction of High Court building, five social activists from Nagaland had submitted a petition to the chief justice of the Gauhati High Court urging to take cognizance of the letter and pursue appropriate course of action.
The activists pointed out that construction works had been delayed even after drawing the entire estimated amount and availing loan from HUDCO exceeding the estimated costs of the project. It may be mentioned that the foundation stone was laid on May 21, 2007 by the then Chief Justice of India, KG Balakrishnan.
Expressing concern over the delay, ACAUT through its media cell Saturday asserted that the state government had much explaining to do before the high court as to whether crores of rupees meant for the construction of the building was misused or not. Lauding the action of five petitioners, ACAUT said that the chief justice of the Gauhati High Court had taken note of the petition and treated the letter as suo motu PIL.
ACAUT stated that the petition/PIL should be an eye opener for the government with the court acknowledging the prayer of the petitioners — Kito Achumi, Odi Jamir, Langwang Konyak, Kevito I Sumi and ST Yapang Jamir.
According to the petition, the initial cost of the new high court building and complex at Meriema, Kohima, was Rs. 43.75 crore, with the foundation stone laid in 2007 along with Manipur, Tripura, and Meghalaya states. While those states have completed high court building construction and started working since 2013, the ACAUT said construction cost of the project was revised similar to all Nagaland government projects. ACAUT alleged that project construction cost revision was basically to loot the exchequer. “Thus, by 2017, the estimated cost of the project had been raised to Rs. 161.10 crore,” it stated.
ACAUT expressed shock that the department in its rejoinder to Nagaland Tribes Council (NTC) claimed that it has already received Rs. 57.61 crore. However, it said that even after 10 years, only 35% of the project was complete.
In addition, ACAUT said an amount of Rs. 22.42 crore had been drawn against construction of Judges’ bungalow. However, according to the petition “there is not even an area earmarked for Judges Bungalow at present”, it stated. Further, ACUAT said that an amount of Rs. 44. 24 lakh was drawn for electrification and water supply works against the non-existent building. 
Besides, an amount of Rs. 1.30 crore was paid as ‘consultancy fees’ against Judges’ bungalow, it stated.
 While expressing gratitude to the petitioners for taking up a very relevant issue at a critical time, ACAUT hoped that more such lawyers and conscientious citizens would come forward to fight against corruption.