Ikiye-Itovi Youth Front (IIYF), government officials, village leaders and contractors of the ongoing construction of PMGSY Phase-IX, Batch -I (2017-18) between Satoi -Itovi- Ikiye on April 29 inspected the construction work and held a joint meeting.
A press release by IIYF media cell stated that the meeting convened by IIYF along with join council Ikiye-Itovi, GBs, council members was held with the executive engineer, SDO spot officer, JE site in-charge, PWD R&B Zunheboto division and contractor, proprietor Nagaland Steel Engineering Works NPW/Class-I/138.
The resolution stated that the contractor should arrange sufficient machineries for early completion; the join council shall detail a volunteer to monitor the construction and make necessary correspondent to all the concerned and extend corporation to the contractor and the department; the council also empowered IIYF to supervise the ongoing construction of work till the completion of work to ensure quality workmanship; the road construction between Itovi to Ikiye shall be constructed with formation cutting as per the DPR; the contractor shall clear all the landslide and construct drainage between Satoi to Ikiye-Itovi on the ongoing construction of work as early as possible; the contractor shall rectify/expand three sharp u-turn location on the ongoing construction of road towards Itovi village.
At the meeting, the release informed that the EE PWD R&B Zunheboto division assured quality workmanship as per the specifications of the work order.