Department of Power Nagaland (DoPN), office of the Executive Engineer (EE) Zunheboto has informed that vegetation clearance of 33KV and 11KV lines under Zunheboto Electrical Division would be carried out from May 17-28, 8 a.m. to 4 p.m., to avoid disruption of power supply due to vegetation.
In a press release, Zunheboto Electrical Division EE, Er. Shiludi Lkr informed that during the period, Zunheboto town shall draw power supply from 33KV Akuluto line. He has also sought cooperation from all the customers.
The following are the schedule for vegetation clearance – 33KV Amiphoto-Zunheboto power house (May 11), 33KV Amiphoto-Satakha (May 17-18), 11KV Asukhoto-Philimi (May 17), 33KV Zunheboto-Aghunato (May18), 11KV Zunheboto-Ghukiye-Sukhalu (May 19-20), 33KV and 11KV Asukhomi-Naltoqa-Suruhuto and 33KV Asukhomi-Kitsakito (May 23-27), 33KV Aichisaghami-Asuto (May 24), 33KV Mokokchung-Akuluto and 33KV Mokokchung-Lumami-NU (May 24-28.