Nagaland NewsLDDU 48 hours NH-702 bandh suspended

LDDU 48 hours NH-702 bandh suspended

The 48-hour NH–702 (Longleng-Changtongya road) blockade jointly called by Longleng District Drivers’ Union (LDDU), Chamber of Commerce & Industries (CCI) Longleng, Longleng Town Students’ Union (LTSU) and Longleng Town Wards’ Union (LTWU), has been suspended. The blockade, which began May 14, was called after PWD (National Highway) department failed to act positively to repair the NH 702.
In a joint press release, LDDU president O. Alemtetba Phom, CCI Longleng president B.Shamkai Phom, LTSU president A. Angmau Phom and LTWU president L.Chuba Phom stated the phase-I agitation blockade was called off after holding co-ordination meeting with PWD (NH) and Gayatri-Maytas company.
At the meeting, the signatories said that the unions placed four-point charter of demands. They said executive engineer NPWD(NH) Mokokchung division and the manager I/c Gayatri-Maytas company have agreed all the demands and assured to start maintaining and upgrading the two lane work project within the deadline fixed by the union. The meeting was held at DC’s conference hall, Longleng.
With regard to the demand for immediate resumption of work (NH-702), the executive engineer (NH) Mokokchung division on behalf of the PWD (NH) and the representative of Gayatri-Maytas Binod Kumar, manager I/c, informed the house that it was not possible to resume the work as the matter was currently under rectification by the ministry of road transport and highways (MoRT&H).
On their second and third demand, the representatives PWD (NH) and Gayatru-Maytas “fully agreed” and gave assurance. Representative of Gayatru-Maytas agreed to carry out maintenance works of the Longleng-Changtongya road till contractual period. He also agreed to keep all the machineries at Longleng district during the entire period of road maintenance.
Further, regarding demand four, both representatives clarified that no subletting of the actual work was carried out under NH-702. However, it was made known to the house that only manual and labour works were hired from local inhabitants as part of the labour force while carrying out the work.
Meanwhile, the meeting also resolved that all frontal organisations of Longleng district would write to the MoRT&H to urgently resume construction of NH-702.
PWD (H) Mokokchung division EE Chubatoshi assured to apprise the chief engineer, National Highway, government of Nagaland, and take up the matter of Longleng-Changtongya NH-702 road with the ministry.