Lotha Hoho (LH) has expressed concern over subletting of rehabilitation works of Wokha- Merapani road by the National Highways & Infrastructure Development Corporation Ltd (NHIDCL) and said that it viewed such act as “malpractice and a hindrance to work quality.”
In a press release, LH chairman, Mhao Humtsoe, and general secretary, Er. Mhondamo Ovung, said that NHIDCL has been authorized to carry out the execution of the rehabilitation works of Wokha- Merapani Road during 2017- 18 for an amount of Rs.190.00 crore.
They claimed that NHIDCL had accepted the tender for the work at 21% below schedule of rate (SOR) and work order issued to the contractor. The signatories also claimed that the contractor for the work was subletting the works to other local contractors. They said that decrease in amount for the work due to lower tender rate at 21% below was Rs.39.90 crore and thus net amount available was Rs. 150.10 crore only.
In addition to this lower tender rate, the LH said the process of subletting would involve fees from the sub-contractors and would further minimize the fund available for the work.
The hoho said it understands that calling and accepting tenders, for contract works, was not only to accept the lowest rate but to ensure that the rate was reasonable and the intending contractor was competent and reliable.
Therefore, it said that NHIDCL accepting a tender rate of 21% below SOR and issuing work order at such extremely low rate and further subletting to sub contractors was seen as malpractice and a hindrance to work quality.
LH said if the contractor was unable to directly execute the work, it should not have tendered for the contract as it only jeopardised the implementation of the work. Further, pointing out that NHIDCL was entrusted to supervise the works for Wokha-Merapani highway, the LH, however, said that during the recent “Colloquium on Road Connectivity” at Kohima, the GM, NHIDCL, Dimapur, could not clarify the queries on the matter, saying that he did not look after this work.
According to the hoho, the GM, NHIDCL Dimapur clarified that GM, NHIDCL, Tezpur, was to look after that road. However, the hoho said GM, NHIDCL, failed to attend that meeting and it insisted that the state government take up the matter with the concerned NHIDCL, Tezpur. The hoho said the state chief secretary stood up and assured to do so.
Stating that it had also written to the NHIDCL through the NH authority, Nagaland and GM NHIDCL, Dimapur for supply of details of the DPR, sanction order, work order etc, the hoho, however, said that till date no communication from NHIDCL has been received.
Nevertheless, the hoho said irrespective of the tender rate, the beneficiary community road users would insist on adherence to work specifications and would not allow any agency to compromise the work quality due to either lower tender rate or sub letting.
It therefore requested NHIDCL to implement the work at the earliest and to adhere to work specifications, without compromising with work quality.
Lotha Hoho stated that Wokha-Merapani road was a historic and traditional road connecting Wokha district with Assam districts of Golaghat and Jorhat as well as Mokokchung and Mon of Nagaland, via Assam, and the state of Arunachal Pradesh is also connected through this road, via Assam.
Stating that the road serves as the survival link for the district, the hoho said the road therefore needed to be declared a full-fledged National Highway and be upgraded as a National Highway immediately.
It also said that the particular road was dependent on the bridge over Doyang river, near Doyang Hydro Project, which had withstood the wear and tear of time and was susceptible to failure any time and needed immediate replacement.