A day after Mokokchung Town Lanur Telongjem (MTLT) served ultimatum on power minister to demanding immediate intervention into the current power crisis in Mokokchung town, the power department, Mokokchung electrical division has requested MTLT to understand some of the factors that were beyond its control.
In a letter addressed to MTLT, Mokokchung electrical division executive engineer (EE) Moa Aier said when the 33/11kv 5MVA power transformer at Mokokchung Power House broke down on August 26 last, there was unfortunately no spare available in the Central Store Dimapur leading to its inability to immediately make any replacement.
EE said repair of such similar capacity transformer normally takes about two months. However, he said fortunately one 5MVA transformer was already under repair at Dimapur, adding that repair of its windings were completed and heating process was on.
Stating that heating process of such capacity transformer was similar to the time taken for curing a concrete slab of the building, EE said the time required was about three weeks or more depending upon weather conditions.
EE informed that this process was scheduled to be completed by September 13.
He also reiterated that after the completion of the process of heating transportation would take another two days, and installation & commissioning another two days provided the weather was clear.