Nagaland NewsPower restoration work underway in Mokokchung

Power restoration work underway in Mokokchung

Works are in full swing to restore power supply in Mokokchung town at the earliest, as the damaged transformer 5MVA after a major repairing in Dimapur was brought to Mokokchung on Sunday morning. 
Mokokchung town suffered heavy load shedding after the 5MVA transformer broke down on August 26 last.  This led the power department use the 2.5 MVA transformer for power transmission, for which residents received electricity only three hours in a day. 
On Sunday, personnel of power department were engaged in full swing in installing the transformer. 
Talking to this correspondent, executive engineer, Er. Moa Aier said the citizens have to wait for another 2-3 days as it takes time for installation and commissioning. He said power supply will effect villages in Asetkong range, Mokokchung town and around 7-8 villages as power supply had been cut in this areas due to ongoing works on Sunday. 
For this, he urged upon the consumers to bear with the inconvenience. 
Earlier, following massive load shedding due to damage of 5MVA transformer, Mokokchung Town Lanur Telongjem (MTLT) had protested as well as appealed to the power department to speed up the repair works. 
A memorandum in this regard was also submitted to power minister by MTLT. Various NGOs had also raised their voice about the crisis and urged the department for early restoration of electricity in the town. 
However, the process of installing and commissioner of transformers takes time and it is yet another 2-3 days away before the department could fully restore electricity supply to its consumers.