Drawing the attention of the state national highway department to the poor condition of NH-2 (erstwhile NH-61) between Tseminyu sub-division and Wokha district, the Rengma Selo Zi (youth organization) on Wednesday stated the road has remained deplorable for more than 10 years due to the “negligent and foul play” of the department and government.
In a press release, RSZ president, Kenneth Kath, recalled that the widening of two lane of NH-61 from KM-40 to 72 KM under Kohima district was sanctioned on June 18, 2010 for an amount of Rs.9368.08 lakh.
Subsequently, RSZ said five bidders were involved in the contract tendering, where M/S Meenakshi Infrastructure Pvt. Ltd was awarded the work though the company was declared non-responsive by the evaluation committee on October 29, 2010 since they did not mention the offer price in Para 1 of the form of bid.
As such, RSZ said the evaluation committee on October 29, 20110 recommended the responsive bidders namely M/S T.Tachu & Co & Velelie Khomo (JV), M/S DRZ-VASCON (JV) to the DG (RD) &SS for approval. However, he said the work was later awarded to M/S Menakshi infrastructure Pvt.Ltd on January 21, 2011 at the cost of Rs.61,75,74,88.80.
Since then, the organisation said the matter was taken to the High Court of Delhi by M/S DRA-VASCON (JV) and M/S Meenakshi Infrastructure Pvt.Ltd also filed an SLP in the Supreme Court of India. Later on August 23, 2013, the Supreme Court dismissed the petition and the matter was withdrawn. However, it alleged that the matter was put under cold storage by the National Highway Department, Government of Nagaland.
RSZ stated that work could not be implemented due to the delayed tactic and foul play of the implementing agency.
Subsequently, it said the Ministry of Road Transport and Highway included the work plan of NH-2 (erstwhile NH-61) in the year 2014-15. However, RSZ said the work could not be sanctioned due to the failure and negligence of the department.
Asserting that the department has been citing ‘technical problem’ over the delay, the RSZ said that it could now no longer tolerate any ‘technical problem’. RSZ stated that it had no hesitation to impose any agitations in any manner within its jurisdiction, as the matter has gone beyond tolerance.
Further, RSZ pointed out that on October 31, 2016, the Ministry of Road Transport and Highway had sent an administrative approval of financial sanction for strengthening and widening of two lane with paved shoulder of NH-61 from KM-40 to 72.40 KM with an approved sanctioned of Rs.340.2687 Crore. As per the directive, RSZ said the work was to be awarded within six months from the issue of the date from the ministry and was supposed to start by December 2016 and completed by November 2019.
In this regard, the RSZ asked as to why the work was not awarded till today to any contractors.
It has also questioned as to why the open tender that was floated in the month of December 2016 was nullified/rejected and why the new tender was floated again on March 7, 2017, when the approved sanctioned was about to be lapsed by April 2017.
Maintaining that it was skeptical about the functioning and system of the department, RSZ said the department has been shifting blame for many years and denying the right of the citizens.
The youth organisation said the department’s attitude clearly indicated that the government or the responsible department was not bothered about the development and welfare of the citizens.
Meanwhile, RSZ cautioned that it would no longer tolerate any injustice, nepotism or favoritism.
While anticipating a positive response on the matter, the RSZ cautioned that failure on the part of the government would compel the organization to impose any sort of agitations within its jurisdiction. The organisation has also appealed to all right thinking citizens and commuters of NH-61 to cooperate and extend solidarity.