Power department has informed that it would be carrying out vegetation clearance of 132kV and 66kV Transmission Lines under Transmission Division Mokokchung from April 15- to May 17, 2025 to provide stable power supply and avoid unwarranted disruption of supply.
In a press release, Mokokchung transmission division executive engineer Hekaito Assumi informed that during the exercise, there would be total shutdown of power from 8am to 4pm daily in order to facilitate smooth execution of the works.
As per the shutdown schedule, Tuensang Tuensang, Noklak and Shamator districts under 66kV Tuensang T/L feeder would be affected from April15-19; areas under 132kV DHEP T/L from April 21-25; Zunheboto district under 66kV T/L feeder from April 28 to May 3; Changtongya Sub-Div, Tull Sub-Div, Longleng & Mon Districts under 66kV Tuli T/L 66kV Naginimora T/L 66kV Tizit T/L 66kV Mon T/L feeder from Mayh 5-10 and Longnak & Mangkolemba Sub-Div under 132kV Longnak T/L feeder from May 12-17. The department has appealed to all public in the affected areas to extend cooperation and bear the inconvenience during the shutdown period.